Chernobyl Confinment 2016 - 2020 ᴴᴰ - Timelapse
WVTCH HD WVTCH HD
6.88K subscribers
4,570 views
0

 Published On May 29, 2019

Description below ↓ | If you like the content please; LIKE, SUBSCRIBE or leave COMMENTS and remarks regarding the channel. Thanks.

High quality videos from WVTCH ᴴᴰ

CONTENT: The New Safe Confinement (NSC or New Shelter) is a structure built to confine the remains of the number 4 reactor unit at the Chernobyl Nuclear Power Plant, which was destroyed during the Chernobyl disaster in 1986. The structure also encloses the temporary Shelter Structure (sarcophagus) that was built around the reactor immediately after the disaster. The New Safe Confinement is designed to prevent the release of radioactive contaminants from the existing shelter, protect the reactor from external influence, facilitate the disassembly and decommissioning of the reactor, and prevent water intrusion.[3]

The New Safe Confinement is a megaproject that is part of the Shelter Implementation Plan and supported by the Chernobyl Shelter Fund. It was designed with the primary goal of confining the radioactive remains of reactor 4 for the next 100 years. It also aims to allow for a partial demolition of the original sarcophagus, which was hastily constructed by Chernobyl liquidators after a beyond design-basis accident destroyed the reactor.

The word confinement is used rather than the traditional containment to emphasize the difference between the containment of radioactive gases—the primary focus of most reactor containment buildings—and the confinement of solid radioactive waste that is the primary purpose of the New Safe Confinement.

November 14, 2016
The arch slipping procedure began

November 29, 2016
The New Safe Confinement slipping was completed, taking a total of fifteen days It was pushed on teflon pads by hydraulic pistons, guided by lasers

November 2017
Development company Rodina began the construction on the first PV project to be developed within the Chernobyl exclusion zone. 3,762 solar modules would be installed at the site with a generation capacity of 1 MW

December 2017
Construction completion is delayed until late 2018 due to a contractor being unable to finish its work in time. The reason is the extremely high level of radiation, forcing workers to limit their presence at the site to a minimum

January 2019
Various subsystems are in operation, including the radiation monitoring system, the back-up power supply system, the fire protection system, as well as lighting, communication, and HVAC

April 2019
Successful conclusion of the 72-hour trial operation test.

Share the video:
   • Chernobyl Confinment 2016 - 2020 ᴴᴰ -...  

We try to make viewers happy and are welcoming them to LIKE, SUBSCRIBE or leave COMMENTS and remarks regarding the channel.

If any of you have some suggestion for any type of videos you would like to see please let us know in the comments below or you can write to us directly if any issues occur.